Non-MotorizedNon-Motorized InfrastructureOther Non-Motorized Projects Completed2009-2018:- Packard/Dalton
Pedestrian Crossing (2009) - Walmart (State & US-12) 10' Greenway (2010)
- Washtenaw/Golfside
Sidewalk Gap Filling (2010) - Maple Road
Bike Lanes (2011) - Carpenter
Mid-Block Crossings (2012) - East West Connector (Ellsworth) Bike Lanes (2012)
- Costco (Ellsworth) 10' Greenway (2012)
- Golfside
Bike Lanes (2013) - Carpenter
Mid-Block Crossing (2014) - Carpenter (Wash. to Packard) Pedestrian Safeway (2014)
- Ann Arbor Saline
Pedestrian Safeway (2014) - Oak Valley
Mid-Block Crossing (2015) - Oak Valley/Bent Trail
Pedestrian Crossing (2015) - Oak Valley/Lohr
Pedestrian Crossing (2015) - Ellsworth/Lohr
Pedestrian Crossing (2015) - Waters/Oak Valley
Pedestrian Crossing (2015) - A2-Saline/Oak Valley
Pedestrian Crossing & New Sidewalk (2015) - Lohr Road
Pedestrian Crossing (2015) - Lohr/Waters
Pedestrian Crossing & New Sidewalk (2015) - Waters Road
Pedestrian Crossing (2015) - Oak Valley/Boulder Ridge
Mid-Block crossing (2015) - Oak Valley/Weatherstone
Bus Stops (2015) - Platt/Hidden Creek S
Pedestrian Crossing (2015) - Platt (Multicultural Academy) Mid-Block Crossing (2015)
- Crane/Amber Way
Mid-Block Crossing (2015) - Oak Valley
Mid-Block Crossing (2015 - Washtenaw
Sidewalk Gap Filling (2016) - Spring Lake Boulevard
Lake Forest Sidewalk (2017) - Glencoe and Washtenaw
Stoplight (2017)
RoadsOther Roads Projects Completed 2009-2018:- Arbor Woods Traffic Calming (2009-2010)
- State St./Runway - Left Turn (2010)
- Carpenter - Overlay (2011)
- Platt - Overlay (2012)
- Ellsworth - Overlay (2012)
- Golfside - Road Diet (2013)
- State & Ellsworth - Roundabout (2013)
- Carpenter/Packard - Safety Project (2013)
- Cloverlane Traffic Calming (2014)
- Dayton Traffic Calming (2014)
- Dalton Traffic Calming (2014)
- Carpenter (Packard - Wash.) - Road Improvement (2014)
- A2-Saline (Oak Valley - Eisenhower) - Resurfacing (2014)
- Lohr/Lohr Circle - Road Improvement (2014)
- Carpenter (Bemis - Merritt) - Safety Project (2014)
- Crane (Michigan - Textile) - Ditching/Milling/Overlay/Shoulders (2015)
- Oak Valley (Lohr - A2-Saline) - Resurfacing (2015)
- Moon Road (Bemis - US-12) - Resurfacing/Widening (2016)
- Traffic Calming - seed humps and signs
Cloverlane, Cole, and Crystal Dr (2017) - Local Road Maintenance
Bemis, Brookview Highlands, Boulder Ridge, Dalton Avenue, Morgan Road, Waterways (2017) - Local Road Maintenance
Campus Parkway (2018) - Primary Road Improvements
Crane Road, Platt Road (2018) - Local Road Improvements Bond Project (2019)
Transit | 
 |