US-12 Wastewater Improvements
Posted on: April 1, 2022[ARCHIVED] Tentative Work Activities for the week of April 4, 2022
US-12 WW Improvement to begin excavation in Hickory Woods Park beginning Monday, April 4, 2022. Daytime closures of Munger Rd between Morgan Rd to Textile Rd are planned. Bus routes, Postal Deliveries, and Rubbish haulers will operate as normal.
WHERE:
WORK TYPE:
- Dewatering Wells Pumping will continue to run during the month of April ahead of the excavation.
- Excavation and Pipe Installation are scheduled to begin Monday, April 4, 2022. Work will begin at the East end of Hickory Woods Park and continue West through the park to Crane Road during the month of April.