Project work has begun. Tree clearing and project staging is currently underway. the following work is currently planned:
March 6, 2023
- ON US-23: NB/SB US23 nightly closure on 3/10, 3/11 and 3/12. US-23 traffic to Utilize Willis Ramps (on and off ramps), Cable barrier removal at specific locations (south of Stony Creek) utilizing a nightly inside lane closure tentatively Sat-Sun 3/4-3/5 pending weather, NB outside shoulder and right lane closure for milling and corrugation filling, Sign removals, surveying work delivering/setting up traffic control devices.
- US-12 Interchange: WB shoulder closure (continuing) and NB US-23 exit ramp to US-12 ramp traffic shift at intersection (3/6 and 3/7, 8 to 5pm) Hydrant relocation at NW quadrant of US/12/US-23, storm sewer, sign removals on US-12, surveying work, SESC measures, setting up/delivering traffic control devices.