News Flash

US-12/US-23 Bridge & Interchange Improvement Project

Posted on: March 10, 2023

US-12/US-23 Bridge and Interchange Project Updates

Project work has begun.  Tree clearing and project staging is currently underway.  the following work is currently planned:

March 9, 2023

  • ON US-23:   Potential northbound outside shoulder and right lane closure for milling and corrugation filling, sign removals, cable barrier removal at specific locations (South of Stony Creek and North of I-94), surveying work, delivering/setting up traffic control devices.      
  • US-12 Interchange:  Potential westbound shoulder closure along US-12, excavation at the interchanges, sign removals on US-12, surveying work, installation of Soil Erosion Sedimentation Control measures, setting up/delivering traffic control devices



Additional Info...