US-12/US-23 Bridge & Interchange Improvement Project

Posted on: March 17, 2023

US-12/US-23 Bridge and Interchange Project Updates

US-12/US-23 Bridge and Interchange Weekly Update:

March 17, 2023

  • On US23:    Inside lane closure for temporary concrete barrier/crossover construction, outside patching will begin on NB US-23
  • US-12 Interchange:     Ramp A (NB US-12 exit to US-12) will begin work, first with the installation of the temporary signal poles.  Excavation continues at interchanges for utility relocations.  Sign removals will begin on US-12.  Soil erosion and sedimentation control measures will continue to be installed and maintained.