US-12/US-23 Bridge and Interchange Weekly Update
On US-23: Shoulder closures will occur thru 03/26 for the filling of corrugations. A single lane closure will occur from 3/27 to 3/29 nightly for lane 2. Pavement markings will be done on 3/29 for traffic shift to outside shoulder. The milling of the median shoulder will begin 3/30. A single lane closure will occur 3/31 thru 4/3 for lane 1 patching NB. Sign removals, cable barrier removal, and mass earthwork at US 23 Interchange will continue