US-12/US-23 Bridge & Interchange Improvement Project

Posted on: March 23, 2023

US-12/US-23 Bridge and Interchange Project Updates

US-12/US-23 Bridge and Interchange Weekly Update 

On US-23:   Shoulder closures will occur thru 03/26 for the filling of corrugations.  A single lane closure will occur from 3/27 to 3/29 nightly for lane 2.  Pavement markings will be done on 3/29 for traffic shift to outside shoulder.  The milling of the median shoulder will begin 3/30.  A single lane closure will occur 3/31 thru 4/3 for lane 1 patching NB.  Sign removals, cable barrier removal, and mass earthwork at US 23 Interchange will continue

At US-12 Interchange:   Ramp A,  NB US-23 exit to US-12 will have temporary signal poles at ramp A and ramp D.  Continuing will be the excavations at the interchanges, utility relocation on 3/27 (2 hydrants NW quadrant and storm sewer) sign removals on US-12, guardrail, surveying work, SESC measures.