US-12/US-23 Bridge and Interchange Project Updates
On US-23:
- The traffic shift on NB US-23 started yesterday. 2 lanes maintained on northbound US-23, utilizing the outside shoulder and right lane. Contractors are now working in the median area of NB US-23.
- Nightly single lane closure on northbound US-23 (4/7/23 from 10pm through 6am until 4/10/23)
- Cutting and building grade in the median to include, excavation, aggregate and HMA
At US-12 Interchange:
- Starting 4/11, signals are to be cut over for implementation of traffic shift on 4/12. 1 lane per direction will be maintained on southernly section of US-12 so contractor can begin widening of north side of US-12. Left turn lane open at Carpenter. Driveway maintained at Sams Club for business traffic exiting to WB US-12. Ramps will be open
- Bridge construction starting at US-12 bridge to include abutment and pier construction