US-23:
Along US-23, 2 lanes will be maintained along northbound utilizing the outside shoulder and right lane. The contractor will continue working in the median area of northbound US-23. Paving crossovers will take place south of Stony Creek and north of I-94 interchange.
Contractors will continue cutting and building grade in the median of northbound US23 to include excavation and aggregate. HMA paving will take place on the northbound inside shoulder at night.
Nightly single lane closures are anticipated on northbound and southbound US-23 will continue through 6/1.
US-12 INTERCHANGE:
Beam setting will take place on Monday 5/22 over northbound US23, 11pm-5am, 15 minutes stoppages will occur on northbound US23.
Stage 2 implemented - 1 lane per direction will be maintained on the northernly section of US-12 through mid-July.
Bridge construction continues at the US-12 bridge.
Potential short term flagging operations will occur between 9am-3pm (when traffic allows) for material delivery trucks leaving loop ramps on northwest and southeast quadrants of the intersection of US-23 and US-12.