US-12 / US-23 Bridge and Interchange Project Update for 08/18/23:
US-23
- On Northbound US-23, 2 lanes will be maintained utilizing the outside shoulder and right lane.
- On Southbound US-23, 2 lanes will be maintained, 1 local lane (for ramp access and Southbound US-23 traffic) and 1 express lane utilizing inside median lane of Northbound US-23
- Northbound US-23 will a right lane closure on Saturday, 8/19 from 7am-6pm.
US-12 Interchange
- 1 lane per direction shall be maintained on northern section of US-12 through August.
- There is an upcoming traffic switch on US-12 that will require intermittent flagging operations for implementation. Date TBD. It is anticipated within next 1-2 days. Awaiting contractor confirmation
- Bridge construction continues at US-12 bridge
- The US-12 entrance to Southbound US-23 will be closed through August 31st for ramp terminal construction. The posted detour is to take Platt to Willis ramp to Southbound US-23
- The Southbound US-23 exit ramp to US-12 will be closed through August 31st for ramp terminal construction. The posted detour is US-12 to Eastbound I-94 to US-12
- The contractor is anticipating bridge demolition of second half of US-12 over US-23 next weekend. Work will be done at night. Details on a specific start date not yet confirmed by contractor