Posted on: October 2, 2023
The PRG II Pathway was opened to pedestrian traffic on Monday, September 25, 2023The contractor is still waiting on mast arms, which should arrive late this fall (mid October). The mast arms will have illuminated signs over the crosswalks, as well as flas...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: September 28, 2023
Construction on the Platt Rd Greenway II Pathway project near Platt Rd is nearly complete. Most aspects of the project construction are being finalized. Currently, the pathway remains closed while the contractor places topsoil and grass seed. On...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: September 15, 2023
Work continues for the project on Platt from US-12 to Wall Park:
Erie Construction is still about one week behind schedule.. Erie has paved most of the pathway. The contractor will begin the placement of topsoil in anticipation of restoration. Bi...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: August 11, 2023
Work continues for the project on Platt from US-12 to Wall Park:
Erie Construction is still about one week behind schedule.. Erie has paved most of the pathway and expects to complete the remaining paving this week. The contractor will now start...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: July 25, 2023
Work continues for the project on Platt from US-12 to Wall Park:
Erie Construction is about one week behind schedule but still believe that they will be able to complete on time. Erie is currently completing yard drain installation and placing fi...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: July 10, 2023
Work continues for the project on Platt from US-12 to Wall Park.
- Over the past two months of storm sewer installation along the west side of Platt, the contractor has finally begun to install the new curb in locations along the pathway. As part o...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: May 3, 2023
Work continues for the project on Platt from US-12 to Wall Park.
- The contractor has completed the mainline storm sewer and has graded the projected pathway. Currently, the contractor is stripping topsoil in preparation for placing the aggregate base for th...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: April 10, 2023
PRG II Project Update:
Work is on schedule and continues on the project on Platt from US-12 to Wall Park
- Existing sidewalk has been removed from the future pathway locations
- Storm sewer is being installed to ensure proper drainage for the project a...
Read on...
Additional Info...
Platt Road Greenway II Project